Basalt fiber composite tile installation process
Fifth, install the inclined ridge tile
The inclined ridge tile is installed on the triangular inclined edge of the multi-slope roof. During installation, it should be aligned up and down on the main tile purlin, and the two sections of the inclined ridge tile overlap by 30mm, and the inclined ridge tile is installed.
Six, install the three-way tile
After the positive and oblique ridge tiles are installed, install the three-way ridge tiles, and the three-way ridge tiles are installed at the intersection poles of the three sides. One side of the three-way ridge tile is lapped under the regular ridge tile, and the other two ends are lapped above the inclined ridge tile.
Seven, install the eaves
The eaves should be installed together with the next section of the main tile, and the main tile should be fixed on the purlin with double-layer self-tapping screws. If the eave head of the main tile is too long from the purlin, and the length of the eave is not enough, use bolts to fix it separately.